Project Description

Sawtooth Technologies, LLC installed the Stevenson fiber network in conduit and on Skamania PUD poles. The route is being completed in three phases. As of November 22, all permits and easements with landowners, municipalities, and government agencies have been completed. As of December 2nd, construction and splicing of phase 1 has been completed.

With enough fiber and hardware on hand, the first part of phase two will be completed by December 31st. Further extension across State Highway 14 will coincide with the City of Stevenson road improvement project. This project is scheduled to start in January, 2003. Once the City road project is complete, there will be ample conduit and fiber serving local business in downtown Stevenson.

The final leg of the project connects to 1st Street., where the Port of Skamania County is planning to construct fiber from the waterfront and Port Business Park.

For input or information on this project please contact the below parties: